Material Delivery Tracker

Material Delivery Tracker is an AI-assistant skill for construction procurement teams and developers, but its Python example keeps working records only in memory. It defines delivery schedules, receipt quantities, status summaries and Excel exports; live shipment tracking and storage-capacity enforcement are not implemented.

Researched 17 Nov 2026

In short.

Material Delivery Tracker is an AI-assistant skill for construction procurement teams and developers, but its Python example keeps working records only in memory. The implementation organizes purchase orders, delivery items, receipt quantities, priorities and storage labels, with summary calculations and Excel export. It requires manual status updates, has no built-in reload mechanism and can assume full receipt when quantities are omitted. Compatibility, reliability and claimed business savings are not established by execution evidence.

Researched and written by an AI model and checked by a second AI model. How it works

Covers SKILL.md, claw.json and instructions.md in 1_DDC_Toolkit/Cost-Management/material-delivery-tracker at revision 410ed1e71e4a5c6fd231afd0c8d1e586a9f546e8, together with the root LICENSE and NOTICE.md. Excludes other skills, referenced books, external databases and uncaptured repository content. Findings derive from source text only. No installation, code execution, model interaction, compatibility test, spreadsheet export or construction-site use was performed.

The overview

Identity

Material Delivery Tracker belongs to DataDrivenConstruction's DDC Skills for AI Agents in Construction repository, under 1_DDC_Toolkit/Cost-Management/material-delivery-tracker. The folder contains SKILL.md with embedded Python, instructions.md with assistant guidance and claw.json with OpenClaw metadata. The manifest identifies datadrivenconstruction as the author and declares version 2.0.0.

The original source at the assessed revision is available at [https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction/tree/410ed1e71e4a5c6fd231afd0c8d1e586a9f546e8/1_DDC_Toolkit/Cost-Management/material-delivery-tracker]. The declared homepage is [https://datadrivenconstruction.io].

Assessment

The source supports treating this as a customizable starting point for manually maintained delivery records. Its specific value is connecting purchase orders, vendors, line-item receipts and delivery dates in a small Python implementation that can produce spreadsheet reports.

The stated benefits include fewer delays, lower expediting costs and better storage planning, but no measurements establish those outcomes. The implementation does not demonstrate autonomous vendor coordination, live tracking or complete inventory management. No code was executed for this report.

Users

Likely users include construction procurement coordinators, site logistics staff and developers supporting those teams. The records suit work organized around purchase orders, expected delivery dates, delivery locations, material quantities and named storage areas.

Beginners would need help configuring an assistant host or turning the embedded example into a Python script. The supplied folder has no graphical interface or documented application installer. Developers can inspect and adapt the classes, but must provide their own persistence, validation and integrations.

Capabilities

The Python defines delivery creation, material line items, four priorities and six statuses: scheduled, in transit, delivered, partial, delayed and cancelled. Records can hold vendor contacts, carrier and tracking details, delivery locations, storage labels and delay reasons. Receipt handling records a receiver, date and received quantities.

Queries find upcoming deliveries, overdue deliveries and vendors by a case-insensitive name substring. Summaries count deliveries by status, priority and vendor and calculate an on-time percentage. Excel export conditionally creates Schedule, Items and Upcoming sheets. Storage areas can record capacity, permitted material types and covered status, but these fields do not control delivery allocation.

Using it

Requirements

SKILL.md declares Python 3 and lists macOS, Linux and Windows in its metadata. The embedded implementation imports pandas, and Excel export explicitly uses the openpyxl engine. Neither library has a supplied version pin, and a minimum Python version beyond Python 3 is unspecified.

claw.json declares filesystem permission, OpenClaw 0.8.0 or later and model labels claude-* and gpt-*. These are compatibility declarations rather than demonstrated results. The data model needs project details, purchase orders, vendors, dates, locations and material quantities; consistent units and reliable receipt data remain the user's responsibility.

Mechanism

The assistant guidance describes gathering project data, applying the methods in SKILL.md and presenting structured results. The embedded Python itself uses ordinary deterministic logic and contains no model API calls. Dataclasses describe deliveries, material items and storage areas, while dictionaries hold the active records.

Delivery identifiers use an incrementing counter, and item identifiers extend the delivery identifier. Receiving compares each item's received quantity with its ordered quantity to choose delivered or partial status. The on-time percentage counts delivered records whose actual date is on or before the scheduled date, divided by all delivered records. Date queries run when called; there is no background monitoring or carrier connection.

Setup

For assistant-host use, the manifest points to instructions.md, which references SKILL.md. Keep these files together with the applicable licence notices. The supplied folder does not document a host installation command, so its installation procedure and declared compatibility remain unverified.

For direct Python use, a developer would need to place the embedded implementation in a local module or script, provide Python 3 and pandas, and add openpyxl for Excel export. The quick-start excerpt assumes the tracker classes are already available. No packaged Python module, dependency lockfile or data-loading procedure is supplied.

Example

The documented example creates an Office Tower tracker and schedules a high-priority delivery from ABC Steel Supply seven days ahead, using PO-2024-001, Site Gate A and Laydown Area 1. It adds 50 W8x31 beams and 200 connection plates, then requests deliveries within seven days.

A separate example records receipt by calling receive_delivery with a receiver but no quantity mapping. Reading the implementation shows that this assigns every item its full ordered quantity. It therefore illustrates an assumed complete receipt rather than a verified count. These examples were not run, and no observed output is available.

Assessment & evidence

Limitations

Records reside in memory, and delivery numbering restarts with each new tracker instance. There is no database, reload function, shared-user coordination or audit history. Although instructions mention CSV, Excel and JSON inputs and export options, the Python implements Excel export only, with no file importers. Its export omits fields including vendor contacts, tracking details, receiver and delay reason, so it is not a complete backup.

Receipt handling has important edge cases. Omitting quantities or passing an empty mapping assumes full receipt. Nonempty mappings replace received totals rather than adding shipment quantities, so repeated partial receipts require cumulative totals. The code does not reject negative quantities or invalid status transitions, and a delivery with no items can be marked delivered.

Upcoming queries include overdue scheduled or in-transit deliveries because they have no lower date bound. Overdue queries exclude partial deliveries. The on-time percentage considers delivered records only and returns zero when none are completed; that zero does not demonstrate poor delivery performance.

Storage usage starts at zero and is never updated by receiving materials. Capacity, coverage, material restrictions and storage-area references are not enforced. There is no stock-consumption ledger, automated vendor communication or live carrier lookup. Declared platform support and spreadsheet behavior have not been tested.

Fit rationale

The strongest fit is a developer-supported delivery log: the source defines concrete records and methods for schedules, receipts, vendor queries and spreadsheet output. Those functions support a useful starting point when a team can maintain the data manually.

The broader descriptions of inventory management and optimized storage exceed the implemented controls. Teams needing durable shared records, physical stock balances or automated logistics would need substantial additions. This distinction follows from the supplied implementation; no comparative trial or operational outcome is available.

Alternatives

The source supplies no named competitor comparison. A practical comparison would be a spreadsheet delivery log for simple manual records, or inventory and construction procurement software for requirements beyond the shown implementation.

Compare those approaches against specific needs: durable storage, simultaneous users, cumulative partial receipts, stock consumption, storage-capacity checks and carrier integration. No alternative's features, pricing or performance were assessed from the supplied material.

Evidence

The source comprises all three files in the material-delivery-tracker folder: SKILL.md, claw.json and instructions.md. SKILL.md supplies the Python and usage examples; claw.json supplies the declared version, host requirements and permissions; instructions.md supplies the intended assistant interaction and file-format claims. The repository's root LICENSE and NOTICE.md supply the applicable legal context.

The available material contains no execution results, automated tests, benchmark results, installation receipts or deployed-project outcomes. Business benefits and platform compatibility therefore remain claims rather than demonstrated results. Scope excludes other repository skills, the referenced book and external databases.

Access & freshness

Costs

The MIT licence permits use and modification without a licence fee, subject to its notice requirements. The Python example contains no paid API calls. Assistant-host charges, model usage, computing costs, setup effort and ongoing maintenance costs are unknown. The source provides no quantified savings or operating-cost estimate.

Rights

The root LICENSE grants MIT rights, and NOTICE.md explicitly applies MIT to skill instructions and documentation. Use, copying, modification and commercial redistribution are permitted, provided the copyright and permission notices accompany copies or substantial portions. The copyright holder is DataDrivenConstruction, dated 2026, and the licence provides the material without warranty.

The referenced Data-Driven Construction book and DDC CWICR database have separate terms described in NOTICE.md; they are outside this skill folder and are not dependencies of the shown Python. The skill's MIT terms do not establish redistribution rights for those materials. NOTICE.md also describes the skills as informational assistant instructions rather than engineering, legal or safety advice.

Freshness

The available source snapshot is revision 410ed1e71e4a5c6fd231afd0c8d1e586a9f546e8, captured on 17 November 2026 at 11:24:58.190 UTC. Its claw.json declares version 2.0.0. The capture timestamp identifies the snapshot's acquisition time, not a release or maintenance date.

No release history, changelog, last-maintained date or evidence of a newer version is supplied. Current compatibility with OpenClaw, model families, Python and spreadsheet libraries is unknown.

Next steps

First decide whether to use the assistant-host package or adapt the embedded Python. Confirm the required dependencies and host compatibility, then compare a small representative project's records and exported sheets with the original delivery documents.

Before relying on ongoing records, add persistence and input validation, clarify cumulative receipt handling and decide how partial overdue deliveries should appear. Check omitted and empty quantity mappings, repeated partial receipts, empty deliveries and exports. If storage planning is required, implement usage updates and capacity checks. These are recommended validation tasks; none has been performed here.