In short.
Project Sizing Guide is an AI-assistant skill for developers and project leads planning software effort, but its uncertainty bands and default conversions are assumptions rather than demonstrated forecasting accuracy. Its instructions organize requirements into work packages and guide the choice between three-point estimation, T-shirt sizing and function point analysis. A standard-library Python script calculates totals and produces JSON or console tables. Important limits include fixed sizing mappings, no dependency or staffing model, incomplete input validation and Chinese output labels. The supplied evidence contains no execution results or comparison with actual project outcomes.
Researched and written by an AI model and checked by a second AI model. How it works
Coverage includes the complete captured skills/project-sizing-guide/SKILL.md, scripts/estimate_calculator.py and folder-level LICENSE, plus the repository LICENSE supplied as a related notice outside the selected folder. All refer to revision c8f12ba31081ce52578dea413c74789ab5437829. Other repository skills, newer revisions and the contents of cited external references are outside this scope. No code was executed, assistant integration exercised, runtime compatibility tested or estimation accuracy measured.
The overview
identity
Project Sizing Guide is the project-sizing-guide skill in zebbern/claude-code-guide. The captured folder contains SKILL.md, scripts/estimate_calculator.py and LICENSE. It supplies instructions for an AI assistant and a separate calculation helper.
The original source folder is [https://github.com/zebbern/claude-code-guide/tree/main/skills/project-sizing-guide]. The captured source revision is c8f12ba31081ce52578dea413c74789ab5437829.
assessment
The resource offers a useful structure for making estimation assumptions explicit: break down requirements, choose a method, record inputs and explain risks. The calculator makes arithmetic repeatable, while the written guide adds questions about technical debt, testing, deployment and team conditions.
The evidence does not establish the guide's claim of scientifically grounded estimates. No completed-project dataset, calibration study or measured forecasting accuracy is supplied. Treat its figures as planning scenarios that need team review, particularly before using its suggested external quotation amounts.
users
Developers, technical leads and project managers can use it to discuss feature effort, sprint workload or an initial quotation breakdown. Beginners receive definitions and a report template; experienced estimators can inspect the formulas, function point weights and calculation code.
Its T-shirt workflow suits early conversations with limited detail. Three-point estimation requires plausible optimistic, most-likely and pessimistic effort values. Function point analysis requires enough knowledge of application boundaries, data groups and transactions to classify them consistently.
capabilities
The PERT calculator returns per-task expected effort, standard deviation, spread ratio and a risk label. It aggregates effort and variance and reports bands labeled 68%, 90%, 95% and 99.7%. T-shirt mode converts XS through XXL into fixed optimistic, most-likely and pessimistic values, then uses the same PERT calculation.
Function point mode counts internal logical files, external interface files, external inputs, external outputs and external inquiries using supplied complexity levels and weights. It converts the total to effort using a configurable hours-per-function-point factor and displays 15% and 30% buffer scenarios.
The command-line helper supports JSON output by default and a console table option. The guide also supplies a work-breakdown process, adjustment checklist and report template; these broader planning steps are not automated by the calculator.
Using it
requirements
The assistant workflow needs a requirements description and informed decisions about scope, work packages, uncertainty and team productivity. The calculator accepts already prepared task or component data; it does not independently derive estimates from project requirements.
The script imports only Python standard-library modules. Its evaluated list and dictionary type annotations indicate Python 3.9 or later, although a supported minimum version is not explicitly documented and runtime compatibility is untested. Using the instructions as an assistant skill also requires a host that can load them; supported hosts, versions and installation locations are not established.
Use consistent units. Although the guide allows person-hours or person-days for three-point estimates, the calculator labels PERT output as person-days and has no unit option. Its function point conversion assumes eight hours per person-day.
mechanism
For each task, expected effort is E = (O + 4M + P) / 6 and standard deviation is σ = (P − O) / 6. O, M and P represent optimistic, most-likely and pessimistic effort. Project effort is the sum of task expectations; project standard deviation is the square root of summed task variances.
The interval calculation uses fixed multipliers of 1, 1.645, 2 and 3 and clips negative lower bounds to zero. Interpreting these bands as probabilities requires distributional assumptions and uncorrelated task errors that the script does not evaluate. It contains no covariance, dependency, critical-path or staffing calculation, so total person-days do not establish a calendar delivery date.
Function point mode multiplies component counts by complexity weights, sums unadjusted function points and applies hours per point, defaulting to 10. The optional value adjustment factor described in the guide is not implemented. The risk label in PERT mode is a simple pessimistic-to-optimistic ratio, not a calibrated probability of failure.
setup
Obtain the skill folder from the original repository, retaining SKILL.md, the scripts directory and applicable licence notices. Make the instructions available through the chosen assistant's skill-loading mechanism. The supplied materials do not specify an installation directory or verify automatic discovery.
For the helper, work from the skill folder and invoke python3 scripts/estimate_calculator.py. Select --method pert or --method tshirt with --tasks containing a JSON array. Select --method fpa with --components and optionally --hours-per-fp. Add --output table for a console table instead of JSON.
The captured calculator source is available at [https://raw.githubusercontent.com/zebbern/claude-code-guide/c8f12ba31081ce52578dea413c74789ab5437829/skills/project-sizing-guide/scripts/estimate_calculator.py]. These are usage instructions; no installation or execution result is established.
example
The guide's login example can be expressed as: python3 scripts/estimate_calculator.py --method pert --tasks '[{"name":"User Login","O":2,"M":3,"P":8}]'. Here the three input values should represent person-days if the calculator's output labels are to be accurate.
Applying the documented formula gives expected effort of approximately 3.67 person-days and a standard deviation of 1 person-day. This is illustrative arithmetic, not an executed calculator result or evidence that a login feature will take that long. The scope, implementation conditions and estimate inputs still need justification.
Assessment & evidence
limitations
The T-shirt mappings, productivity ranges and suggested percentage adjustments are supplied defaults without supporting calibration data. The guide permits teams to customize sizing, but the helper exposes no command-line option to replace its size mapping. Most checklist adjustments require separate judgment and calculation; overlapping allowances could count the same work twice.
Input validation has visible gaps. Reversed O/M/P ordering generates warnings but does not stop calculation. Non-finite numbers are not explicitly rejected. A zero optimistic value produces an infinite spread ratio, which the default JSON serialization can emit as Infinity rather than strict JSON. These are implications of the source code, not observed test results.
Methods, units, risk labels, recommendations, help text and diagnostics include Chinese, with no language option. Function point counting standards compliance is not established. The helper also does not retrieve historical delivery data, model correlated overruns or convert staffing availability into a schedule.
reasoning
Its practical value is in exposing assumptions and applying consistent arithmetic. An assistant can help organize requirements and questions, but neither the instructions nor the calculator establish a team's productivity from requirements alone.
The guide's method choices offer sensible starting questions: use relative sizes when detail is scarce, three-point estimates when work packages can be discussed individually, and function points when functional components can be counted consistently. Increasing numerical detail does not itself increase accuracy.
For decisions involving delivery commitments, the central issue is whether inputs, productivity factors and uncertainty assumptions reflect the actual team. The displayed confidence percentages and quotation suggestions do not resolve that issue.
alternatives
A team that only needs transparent arithmetic could use a spreadsheet implementing the supplied formulas, with explicit units and team-specific sizing tables. That would require maintaining its own calculations and reporting rather than using this assistant skill.
Historical team throughput is a useful comparison when such records exist; the guide itself recommends historical calibration, but the calculator has no data-import or calibration feature. Where task dependencies and staffing determine the delivery date, a separate scheduling approach is needed. No competing product, performance comparison or alternative price was assessed.
evidence
The supplied evidence includes the complete skill instructions, complete calculator source, folder-level MIT notice and repository-level MIT notice. These establish the documented methods, visible implementation and stated reuse permissions.
The instructions name IFPUG, PMI, Steve McConnell and Mike Cohn as references, but their texts and validation of this implementation are not supplied. No installation logs, runtime outputs, tests, benchmark dataset or completed-project comparisons are included. Runtime behavior and forecasting performance remain unverified.
The original captured instructions are available at [https://raw.githubusercontent.com/zebbern/claude-code-guide/c8f12ba31081ce52578dea413c74789ab5437829/skills/project-sizing-guide/SKILL.md].
Access & freshness
costs
No purchase price, subscription charge, assistant tariff or total operating cost is stated in the supplied materials. Actual cost is unknown.
The calculator source contains no model API or network calls and imports only standard-library modules. Using the instructions through an AI assistant may incur that assistant's charges, which are not documented here. There is no evidence quantifying time savings or financial return.
rights
Both supplied licence notices use the MIT License. The folder notice credits 2026 effort-estimator contributors; the repository notice credits 2025 zebbern. They permit use, copying, modification, distribution, sublicensing and sale, subject to retaining the copyright and permission notices in copies or substantial portions.
Both notices disclaim warranties and liability. Preserve both captured notices when redistributing the supplied material. These permissions concern the resource files and do not establish licensing terms for an assistant or other service used alongside them.
freshness
The supplied snapshot was captured on 16 November 2026 at 14:41:08.490 UTC and identifies source revision c8f12ba31081ce52578dea413c74789ab5437829. Findings apply to those captured files.
A separate release version, last maintenance date and contents of newer upstream revisions are unknown. The years in the copyright notices do not establish when the instructions or calculator last changed.
actions
Start with a bounded feature and have the people doing the work review its work packages and inputs. Record scope exclusions, use person-days consistently for PERT and include review, testing and deployment without duplicating allowances.
Calibrate T-shirt mappings and function-point productivity factors against the team's completed work where records exist. Check that numeric inputs are finite and correctly ordered, and inspect output compatibility before feeding JSON into another system.
Before using the results for a delivery date or external quotation, account separately for staffing, dependencies and shared risks. Validate runtime behavior in the intended environment and compare forecasts with actual outcomes; the supplied materials establish neither.